Unplanned stops

Unplanned stops are used on the Lineview page for marking productions stops which are considered as efficiency loss. Example: equipment failure, stops due to organizational issues etc.

Link to OEE: 100 minutes of planned time, 10 minutes of unplanned stops. Unplanned stops reduce availability which results in lower OEE value.

How unplanned stops affect availability?

Planned time = 100min
Unplanned stops = 10min
Operating time 100min-10min=90min
Availability = 90/100*100=90%

Stop reasons can be defined as unplanned on the settings page.